PURPOSE OF THE PROJECT
The promotional capsule labeling system was designed and completely rebuilt, the rewamping concerns all the electronic and electromechanical movement parts of the promotional capsule labeling system.
This choice was imposed on us by the market as the spare parts of the previous system mounted on the machine were no longer available, so after a market analysis we opted for a reconstruction intervention with our internal project rather than the total replacement of the ‘plant.
The goal of this intervention is the design and construction of all the parts no longer available on the market to allow the processing of promotional capsules to be continued, improving their quality and creating a simpler spare parts management system.
CONTENTS OF R&D ACTIVITIES
All the motors that have been mounted for the various movements of the pieces and labels are controlled by inverters while previously they were motors without logic to which a direct start command was given and then in case of slowdown mechanical clutches intervened to vary the speed. .
All the previously electromechanical part has been replaced by totally electronic components which have allowed a more flexible management of the machine and a diagnostic system has been applied to the machine itself which makes intervention times in case of breakdowns much faster.
Machines that carry out this type of processing exist on the market but make the company always dependent on third parties for maintenance interventions with sometimes too high times, instead having our own internal project we have a much faster and more flexible management of the plant.